The following PMP questions are part of our PMI PMP real exam questions full version. There are 416 in our PMP full version. All of our PMP real exam questions can guarantee you success in the first attempt. If you fail PMP exam with our PMI PMP real exam questions, you will get full payment fee refund. Want to practice and study full verion of PMP real exam questions? Go now!

 Get PMP Full Version

PMI PMP Exam Actual Questions

The questions for PMP were last updated on Apr 25,2024 .

Viewing page 1 out of 4 pages.

Viewing questions 1 out of 20 questions

Question#1

A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule
What can the project manager do to move the team to the norming phase?

A. Plan social activities to help foster stronger interpersonal relationships and identify shared goals.
B. Speak with the project sponsor about changing the team composition
C. Figure out who is behind the issues and apply progressive disciplinary techniques.
D. Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Question#2

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?

A. Guide the team to revert back to the forming and storming stages
B. Escalate the issue to the project sponsor.
C. Convene a team building event to address key performance indicators (KPIs).
D. Discuss the decrease in productivity with human resources

Question#3

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available
Why is an attendance list important?

A. It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance
B. The attendance list is evidence that risk review meetings were held with the appropriate project team members
C. It is a record that shows the number of attendees in the meeting
D. It is a document that is registered within the lessons learned register

Question#4

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?

A. Add an entry in the risk log
B. Implement the changes
C. Review target benefits.
D. Improve the team's velocity

Question#5

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.
How should the project manager respond?

A. Tell the junior team member that the information is available in lessons learned
B. Offer guidance and follow up with some developmental activity for the junior team member
C. Inform the junior team member that risk mitigation is not part of their work
D. Refer the junior team member to the senior team member who develops the risk mitigation strategy