We recommend to choose the PSK-I Exam Questions from Testpassport to prepare for your Professional Scrum with Kanban level I (PSK-I) exam well. Testpassport understands the significance of genuine PSK-I Exam Questions. So the professional team of Testpassport have created the latest PSK-I certification Exam Questions to ensure your success.
Professional Scrum with Kanban level I PSK-I Certification Exam

Testpassport Scrum PSK-I Exam Questions Features

Testpassport Professional Scrum with Kanban level I PSK-I Certification Exam Questions have verified answers, which are done by our Scrum certified experts. With Testpassport Scrum PSK-I Certification Exam Questions with verified answers, you can get the desired score for Professional Scrum with Kanban level I PSK-I exam well. Testpassport PSK-I Certification Exam Questions with verified answers aim at helping the candidates to strengthen their knowledge of Scrum PSK-I exam.  

What is the Professional Scrum with Kanban level I (PSK-I) certification exam?

Before getting Testpassport PSK-I Exam Questions, you need to know the details of Professional Scrum with Kanban level I (PSK-I) certification exam. The Professional Scrum with Kanban (PSK I) certification validates your knowledge of how Scrum Teams can use Scrum with Kanban to support value creation and delivery. PSK I ensures that you understand how Scrum Teams can use Kanban. PSK I also tests your ability to apply concepts from the PSK subject areas and in some cases, apply your own experience. 

Real Scrum PSK-I exam has 45 questions, candidates need to answer all these questions in 60 minutes. The passing scoure is 85%. Want to read and study some part of PSK-I real exam questions?  i share some sample questions as below:

1.The basic metrics of flow that Scrum Teams using Kanban will need to track are: (choose the four best answers)
A. Lead Time
B. Velocity
C. Work in Progress (WIP)
D. Cycle Time
E. Throughput
F. Work Item Age
Answer: C,D,E,F

2.What are desired benefits of applying Kanban practices in a Scrum Team? (choose the best four answers)
A. Increased collaboration between the Developers.
B. Scrum Teams are no longer limited by Sprint time-boxes.
C. For a work item, the average cycle time may be reduced.
D. Increased transparency on the Work in Progress (WIP) state of the work items.
E. Uncovering areas of improvement within the Sprint.
F. Removes the need for the Sprint Review resulting in a higher velocity.
G. Scrum Teams can release larger increments in a shorter period of time.
Answer: A,C,D,E

3.How does setting limits to Work in Progress (WIP) policies support self-management? (choose the best two answers)
A. WIP Limits creates a boundary for which the Scrum Team self-manages within.
B. WIP Limits inhibit self-management since they limit the team's autonomy to pull work.
C. As part of self-management Scrum Teams figure out their own WIP Limits.
D. A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.
Answer: A,C

4.According to Little's Law, which of the following statements is true if a team reduces its Work in Progress (WIP) limit? (choose the best two answers)
A. In a given time period, the average number of Product Backlog items (throughput) completed will
likely increase.
B. Average time between starting and finishing (cycle time) of Product Backlog items will likely decrease.
C. Quality of work completed will likely increase.
D. Value of each backlog item completed likely will go up.
Answer: A,B

5.An existing Scrum Team wants to apply Kanban practices. What can the team start doing get begin achieving flow? (choose the best 4 answers)
A. Ensuring the product backlog is refined frequently.
B. Limiting Work in Progress (WIP).
C. Visualizing their workflow.
D. Actively managing WIP.
E. Inspecting & adapting their workflow.
Answer: B,C,D,E

46.A Kanban board is comprised of which of the following policies? (choose the best two answers)
A. Each Product Backlog Item type has a separate swim lane.
B. Your workflow visualization.
C. Work in Progress (WIP) Limits.
D. Class of service policy.
Answer: B,C

With Testpassport Scrum PSK-I real exam questions, you can pass Professional Scrum with Kanban level I PSK-I easily. If you fail Professional Scrum with Kanban PSK-I exam by using our PSK-I exam questions, you can get full refund of PSK-I payment fee in ONE working day after you scan the failed score report and send it to us via [email protected]