Updated Managing Jira Cloud Projects ACP-620 exam questions

Oct 17,2022
If you are attempting the ACP-620 exam for the first time, then you must focus on finding the best Managing Jira Cloud Projects ACP-620 exam questions that will help you clear the exam on your first attempt. You will be guaranteed to pass Managing Jira Cloud Projects ACP-620 exam in the first attempt. All the real ACP-620 exam questions & accurate answers, ACP-620 test questions are prepared by the top industry experts, who have collected the most updated ACP-620 test questions for all. Testpassport Managing Jira Cloud Projects ACP-620 test questions provide the great exam questions and answers help you prepare well and pass ACP-620 Managing Jira Cloud Projects certification exam in the first try.
Managing Jira Cloud Projects ACP-620 exam

ACP-620 Managing Jira Projects for Cloud Certification

ACP-620 Managing Jira Projects for Cloud is is intended for anyone who wants to upgrade themselves in Jira Cloud. This exam covers the knowledge of users who use Jira Cloud as Project Administrators. Before appearing for tougher exams such as ACP-120, it is recommended to test your skills on ACP-620. Testpassport Atlassian ACP-620 real exam questions are available in PDF and Software versions. ACP-620 real exam questions in PDF version is the simplest way for you to read and study all the questions and answers. It can be printed out and shared with your friends. ACP-620 exam questions in Software version is a simulation of real Atlassian ACP-620 exam, and you can feel the real exam environment. You can choose the version of ACP-620 exam questions according to your habits.

ACP-620 Exam Format
Up to 75 questions.
63% is the passing score.
You have 180 minutes (3 hours) to complete the exam.
PRICE USD $100

ACP-620 Exam Topics
Project Creation (10-15% of exam)
Board Configuration (25-35% of exam)
Managing Projects (25-35% of exam)
Automation (15-20% of exam)
Reporting (15-20% of exam)

Share Managing Jira Cloud Projects ACP-620 Sample Questions as below: 
1. Which of the following are true about creating a Jira board (Choose three.)
A. We cannot create a new board while creating a new Jira project.
B. We can create a new board for only one Jira project.
C. We cannot create a new board from someone else's saved filter.
D. We can create a new board formultiple Jira projects.
E. We can create a new board from our own saved filter.
F. We can create a new board from the existing project.
Answer D, E, F

2. Which of the following are true aboutthe Jira permission (Choose three.)
A. You need 'Resolve Issues' permission to reopen resolved issues.
B. You need 'Manage Sprints' permission to complete your sprint.
C. You need the Jira Core application access to create a new sprint.
D. You need 'Resolve Issues' permission to set the 'Fix version' field.
E. You need 'Fix Version' permission to set the 'Fix version' field.
F. You need 'Move Issues' permission to move the issue's status to another status
Answer A, B, D 

3. Which of the following are true about sub-tasks (Choose three.)
A. Sub-tasks can be disabled.
B. Sub-tasks can have sub-tasks.
C. Users cannot move sub-tasks to another project.
D. Sub-tasks can be translated into other installed languages.
E. Users cannot convert sub-tasks to epics.
F. Users can convert sub-tasks to standard issue types, and vice versa.
Answer A, D, F

4. Sarah created a new custom field called 'Project Cost'. She cannot view the field in some of the issues.
Which of the following is true
A. Some issues have 'Issue Level Security' applied.
B. 'Project Cost' value is empty.
C. 'Project Cost' is one of the 'Hidden fields'.
D. She needs 'Browse Projects' permission.
Answer B

5. Which of the following are suitable scenariosto use Jira group (Choose four.)
A. The project administrator will manage group membership.
B. Members of the group are responsible for making bulk changes on multiple issues.
C. Same users will be working on multiple projects.
D. The site administrator will manage group membership.
E. Permission can be managed at the global level.
F. Team members require 'Work On Issues' permission to log work done.
Answer B, C, D, E